› Power cables and transformer substation installed
› Pump stations constructed, completed installation of pipelines
› Parking lot for the construction works prepared
and other works
Production plant:
› Ground works to the level of zero point and ground removal completed
› Most of the works on foundations for the supporting constructions are completed
› The basin of tank farm is completed, completely finished works on concrete placing and hydraulic insulation, the supporting foundations for the equipment in tank farm are in place
and other works
Main pipeline:
› Installation and laying in trenches of pressured and gravitational pipelines for transport of pregnant leach solution has started
› Installation and laying in trenches of technical water pipeline has started
and other works
Work pond:
› Clearing of the vegetation and sediments and removal of the material from all territory of the work pond is completed
› Berms of the work pond are constructed
and other works
Accumulation pond:
› Construction of the approach road is completed
› Clearing of the vegetation and sediments and removal of the material from all territory of the accumulation pond is completed